Assignment Task

You are bidding on a contract to carry out a major reforestation effort that remediates an area of land  previously used for high-impact logging (clearcutting). The goal of this work is to distribute seedlings over  the area following reforestation best practice. You are competing for this contract with others, and the  lowest bid usually wins the work. You need to figure out what your costs will be in order to quote a  competitive price in your bid. 
SCOPE OF WORK 
The project scope includes: 
• Purchase an adequate supply of seedlings 
• Set up a base camp near the planting site 
• Arrange transportation to get planters from base camp to the subject land each work day • Cover the entire plot of land with seedlings 
• Space seedlings apart to achieve the target density 
• Plant each seedling properly to maximize the chances of growth 
• Tear down the base camp when planting is done 
The subject land is between 50 and 130 hectares in area. It is serviced by a single forestry road that is only  usable between the start of June and the end of August. The access road terminates approximately in the  center of the subject land, which is ideal since planters can start from this point and complete planting  loops each work day. 
Seedlings are planted manually by a group of (usually) college students. Each planter has a backpack full  of seedlings and some specialized planting tools to enable rapid planting over rough terrain. A typical  planter can plant between 110 and 150 seedlings per work day. Seedlings are planted at a mean density of  one seedling per five square meters. They cost $0.70 each. 
Planters are housed at a base camp for the duration of the job. The base camp has tents, sanitation  facilities, and a kitchen. The base camp is 30 minutes by truck from the plant site. The base camp has a  fixed operating cost of $500 per day, and a one-time fixed setup/strike cost of $2000. The base camp  cost includes a truck for transporting planters.
Planters work from 0700h to 1500h six days per week. They are paid from $1.39 to $1.79 for each planted  seedling. They are not paid by the hour, so they can choose when to take their own rest and lunch breaks.  In addition, each planter is paid a $1000 bonus upon completion of the project. 
The planting supervisor follows planters at random to inspect the quality of work and ensure seedlings are  planted properly. The supervisor is paid a daily flat rate of $300. 
Your task is to figure out what your net job costs will be, and then add a markup to cover your overhead  and make a profit. Your markup rate is 30%. 
This assignment is intended to help you understand how projects are constrained (the iron triangle) and the  relationships between effort, duration, and elapsed time. When you create your quote: 
• Assume all planters can plant seedlings at the exact same rate per work day. 
• Assume all planters remain with the project until completion and thus earn the bonus.

• For planning purposes you can assume each month has exactly 30 calendar days.

• For planning purposes you can assume each month has exactly 25 working days.

• Try to build a quote using the minimum number of planters. 
• You cannot allocate a partial planter. If you discover you need 20.5 planters, you need to hire 21. 
Important! You will be assigned one of the following variations by your instructor. Make sure you use the  values for the variation you are assigned! 

 

This Management Assignment has been solved by our Management Experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.