Assignment Task -                 
 

Commence

You are the chief estimator of Builders for the Coast Pty Ltd. They have been invited to tender for the construction of a new house for Reedy Creek Shire at Lot 3 Annabelle Avenue Newtown Qld.

1.Explain why you would need to visit the building site and verify the location, access to site, existing buildings on the site and neighbouring buildings, existing trees and contours.

It better to visit the building site and verify the location to make a condition report. a condition report is a report on the site conditions that exist prior to building commencing. This requires an investigation of the site, during which a site supervisor becomes aware of any potential difficulties that may arise such as:

 • Existing condition of the site such as trees, vegetation, slope, aspect to north

 • Any existing services that require removal 

Any legal problems arising from boundaries, e.g. there may be a dispute over boundary 

Any features of neighbouring properties that will require attention and/or protection from future damage claims, e.g. a pool close to the boundary may require protection if excavation is to take place.

 

2.Prepare all the tender documentation that is in the “Request for Tender” according to company standards after identifying all the information and supporting documentation needed for the submission of the tender. 

 

  1. Attach all the vital information, specifications and drawings to the tender.
  2. Include a list of subcontractors you will use.
  3. Comment on how you could be sure that you have attached the necessary documentation. 
  4. Outline the evaluation process you would use to ensure that all completed tender documentation and calculations are checked and conform to the company financial and administrative guidelines.

 

3.Explain how you chose which contract to use for this tender response?

  1. Which of the following would you need to take into account when preparing this tender? (More than one answer may be correct)

  2. Applicable Australian standards
  3. BCA
  4. SDS
  5. Site conditions
  6. Type of building 
  7. Qualifications of the Architect  
  8. Company procedures 
  9. Plans and specifications 
  10. Tender ammendments

Explain, in a few sentences, a major risk that would need to be considered when preparing this tender?

  1. Comment on the following statement: 

As long as you have followed the company procedures for the tender submission you don’t need to check the Request for Tender document again.”

  1. After you have prepared the tender, from whom do you need approval before submitting the tender?

  2. Comment on why is it necessary to check the format of the tender and type of delivery method for the submission of the tender?

  3. Comment on why you would need to allow sufficient time to submit this tender?

  4. Using the ‘Shire of Reedy Creek House Plans.pdf’ calculate the amount of floor tiles required for the Laundry, Bath, WC and Ensuite and the labour to lay them using the following formulas. Estimate the cost of tiles and cost of labour for laying the tiles. The bath is 700mm wide and is not tiled below it. You will need to tile under the vanities and laundry tub.

  5. Floor tiles – calculate the square metres required with an allowance of 10% extra for wastage and cost these at $50.00 + GST per square metre. 

  6. Labour for laying. Subcontract cost to lay is $45.00 +GST per square metre.

  7. How long would it take the tiler to lay the floor tiles if he could lay 1.2 square metres of tiles per hour?  (Provide the answer to the next full hour.)

  8. Using an appropriate costing software package such as Excel or Estimating software, estimate the cost of the building using the following rates:

    1. Main living areas @ $1350 per square metre = 

    2. Garage @ $1050 per square metre =

    3. Alfresco and Patio @ $850 per square metre =

 

  1. Explain the advantages and disadvantages of using either employees and/or subcontract labour on the proposed job.

  2. Comment on what communication skills/strategies would you need to use to communicate with a range of people including industry professionals and persons with diverse social, economic and cultural backgrounds and with varying physical and mental abilities

  3. Comment on what information is essential for the preparation of this tender?

  4. Explain, in a few sentences, why it is necessary to follow company procedures in the preparation of this tender?

  5. Explain, in a few sentences, why you would conduct a preliminary evaluation of the tender documentation?

    1. Explain the process you would follow to obtain approval or endorsement from the manager for the submission of the tender documents. 

 

 


This Engineering Assignment has been solved by our Engineering Experts at onlineassignmentbank. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment Experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.
    

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.