Question 1
A link traverse started on a known trigonometrical station (T2), runs along a route to four traverse stations (A, B, C, D) and closes on another known trigonometrical station (T4). To provide angular check, an opening back bearing was established from T2 to T1 and a closing forward bearing from T3 to T4. Coordinates for all the known stations are given.
The following field data are provided for the link traverse:
Table 1: Link Traverse Field Data
STATION HORIZ. ANGLE
(measured in a clockwise direction) POINTINGS FR TO HORIZ.
DISTANCE
(m)
T2 75° 46’ 46” T1-T2-A T2 - A 97.453
A 219° 27’ 26” T2-A-B A - B
90.737
B 217° 42’ 45” A-B-C
B - C
91.849
C 174° 49’ 40” B-C-D C - D 116.413
D 158° 34’ 40” C-D-T3 D - T3 103.829
T3 261° 27’ 26” D-T3-T4
Table 2 : Given Coordinates
STATION Northing (m) Easting (m)
T1 1451.500 495.654
T2 1353.493
490.126
T3 1076.826 839.109
T4 992.075 788.116
-Produce a large, labelled sketch of the traverse showing all the measured data.
-Calculate the angular misclosure and adjust the angles for closure.
-Calculate the bearings of all traverse legs.
-Calculate latitude and departure values for all traverse legs.
-Calculate linear misclosure and proportional accuracy for the traverse.
-Adjust the traverse for closure using the Bowditch method.
-Calculate coordinates for all traverse stations.
-Calculate the area enclosed by the stations T2-A-B-C-T2.
-A rectangular building is to be set out within the enclosed section mentioned at (h). Determine coordinate values for the building given the following information:
Building corner #1 (b1) is to be placed at a distance of 48.900 m from Station A with an angle of 25° 15’ 30” turned clockwise from Station A with Station B as reference object.
Building corner #2 (b2) is to be placed at a distance of 30.995 m from Station B with an angle of 75° 39’ 51” from Station B with Station C as reference object. The distance between b1 and b2 represents the length of the building and its width is 25.000 m.
Show the building on the sketch with its labels and dimensions.
This CENG120 - Engineering Assignment has been solved by our Engineering experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.
Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.
© Copyright 2026 My Uni Papers – Student Hustle Made Hassle Free. All rights reserved.