Demolition planning requirements
The following need to be considered before demolition commences to decide which of these are necessary depending on the nature of the demolition:
details of the demolisher and appropriate licencemethod of demolition - either manual or mechanisedextent of temporary fencing and hoardings
protection of adjoining properties, existing buildings and infrastructure disconnection notices for the service authorities, electricity, water, gas and telecommunications
the order in which the structural systems will be removed (the sequence of operations) details of any hazardous materials and notification of these to relevant authorities
on-site amenities such as toilet, first aid, fire services control measures for dust, noise and vibration vermin control for rats and mice traffic control on and off the site
truck wash bays environmental considerations such as recycling.
Structures
•Identify materials, eg. primary, structural and secondary lining materials.
•Locate hazardous materials and notify authorities as required by OHS legislation.
•Identify any special structural systems, eg. post tensioning, bracing systems, elements resisting vertical loads, elements resisting horizontal loads.
A photo of a house is shown.
Services
•Locate and identify services and supply mains, eg. water, electricity, gas and extent of wires and pipes.
•Locate and establish the extent of other services such as sewerage and drainage.
A photo of a run-down building is shown.
Site
•Locate depths of adjoining property footings where the building being demolished is close to the boundary or is likely to have an effect on the adjoining property.
•Notify the building surveyor if any form of protection of the adjoining property is required.
•Examine and record the condition of adjoining buildings particularly where they are close to the property boundary.
•Locate and identify any common support structure for the adjoining property.
•Determine the location of any underground tanks.
•Determine suitable site entry points for personnel, plant and equipment and access to and from the site for vehicles.
•Determine crossing and infrastructure protection by hoarding or crossover boarding.
A photo of a house without a roof and rubbish in front of it is shown.
Demolition procedure
Pre-demolition
•Disconnect all services, power, water, gas etc.
•Locate stormwater and sewer drains and seal at points of discharge.
•Protect adjoining property as required by the building surveyor.
•Provide temporary wall bracing and shoring where required.
A photo of a run-down building is shown.
Demolition begins
•Remove loose or attached fittings and built-in fixtures, internally and externally.
•Remove external wall cladding, attached chimneys, outbuildings and lean-to structures.
•Remove internal linings.
A photo of a building with a demolished roof is shown.
Going 1
•Make sure the building is adequately braced during the removal of cladding.
•Remove plumbing and electrical wires and pipes.
•Remove roof covering and restraining and loose materials to avoid possibility of materials being airborne.
A half demolished building with a fence around the site is shown.
Going 2
•Remove roof structure and provide temporary bracing and shoring as required.
•Remove wall panel or framing and provide temporary bracing and shoring as required.
•Remove floor structure.
•Remove footings.
A photo of a truck and crane removing rubbish from a site is shown.
Gone!
•Clean up site.
•Fill in excavations.
•Check for any hazards.
•Clean site entry points and infrastructure where necessary.
A photo of a cleared site with a fence around it is shown.
Conclusion text
Note the following points:
•The demolition must always be supervised by the demolisher.
•The site must be fenced or suitably barricaded to prevent public access during the demolition process.
•No part of any external wall on or within 6,000 mm of the street alignment is to be pulled down except during times as specified by the building surveyor.
•Where asbestos or materials containing asbestos are involved in the demolition works, compliance with Work Cover or Work Safe legislation must be maintained at all times.
This CPCCBC4010B - Engineering Assignment has been solved by our Engineering experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.
Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.
© Copyright 2026 My Uni Papers – Student Hustle Made Hassle Free. All rights reserved.