1. The jobs of the following network have the indicated time estimates as shown in the Table
|
Job |
Optimistic |
Most Likely |
Pessimistic |
|
(1,2) |
3 |
6 |
15 |
|
(1,6) |
2 |
5 |
14 |
|
(2,3) |
6 |
12 |
30 |
|
(2,4) |
2 |
5 |
8 |
|
(3,5) |
5 |
11 |
17 |
|
(4,5) |
3 |
6 |
15 |
|
(6,7) |
3 |
9 |
27 |
|
(5,8) |
1 |
4 |
7 |
|
(7,8) |
4 |
19 |
28 |
Draw the project network
Calculate the length and variance of the critical path
What is the probability that the jobs on the critical path will be completed by the due date of 41 days
What is the probability that the jobs on the next critical path will be completed by the due date
What is the estimate that the entire project will be completed by the due date
Using standard PERT assumptions what is the probability of completing the project