Assignment Task:

The Board has asked Grace to prepare the initial baseline plan which will include the scope, schedule and cost baselines. Grace will present the plan to the Board on Friday the 8th of May. 

Grace brings you in to help guide the project. She knows that you are studying project management at ECU and you see this as an opportunity to apply what you have been learning. You know that this is a big project and that the board has high expectations of Grace. You want to be sure everyone meets these expectations so the board will approve the budget needed for this project. However. they will only do that if they are confident that Grace has a detailed plan for how she will get it all done. If approved, she will then have six months, from May 15 to November 15, to implement the plan and complete the project. 

Deliverables: 
You are required to form a group prior to module 3. The deliverables which will be assessed will be an integrated project baseline plan that includes the following plans. 

1. Cost Baseline Plan including: 
a. Bottom-up Budget 
b. Cost Baseline 

2. Scope Management Plan 
a. Scope statement 
b. WBS 

3. Schedule Management Plan 
a. Resourced schedule which shows Critical path 

4. Other items 
a. Your plan should accommodate a resource plan 
b. Activities, materials and equipment sourced externally should follow the procurement steps discussed in class 
c. The plan should be integrated into a business report structure 
d. The plan should be based on the minimum requirements detailed in the project scenario above however you should research and include any other information that is needed and set out how and where you would source it. 


This Management Assignment has been solved by our Management Experts at onlineassignmentbank. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.