Question 1

Activity X takes 4 days, its Early Start Time is Day 20 and its Late Finish Time is Day 24. Which of the following is true?

a) The float for this activity is 4

b) Activity is on the critical path

c) This is the last activity of the project

d) Its Early Finish Date is 20

 

Question 2

Which of the following is not a project? a) A team designing a new car b) A husband preparing a special dinner for his daughter c) A construction company building an airport d) A production team assembling a mobile phone

 

Question 3

The project manager has just met with her team to discuss ways to reduce the impact and probability of identified risks. This meeting would be an example of:

a) Risk mitigation

b) Risk control and documentation

c) Risk identification

d) Analysis of probability and consequences

 

Question 4

Kate is putting together her budget for the project and as part of this process she is discussing estimates from each member of the project team. She presents her budget to senior management and John rejects it, stating that he wants her to shoot for a given lower figure. John is employing what method for project cost budgeting?

a) Bottom-up

b) Top-down

c) Parametric

d) Comparative

 

 

This (LSBM204) Business Management Assignment has been solved by our Business Management experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.
Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.