Highlights
Task 1: Prepare the schedule in Primavera P6 for constructing the bridge shown below. Assume the project starts on 1st June 2020 and all seven days in every week is a working day in this project.
a) The work starts with the construction of the foundation (F) for the two piers (i.e. both
Pier 1 and 2) simultaneously. Duration of this activity is 18 days (each). b) Construction of the pier columns (C) starts soon after the foundations are finished. It takes 16 days to construct the columns. c) Construction of the two abutments (A) (i.e. both Abutment 1 and 2) can also proceed in parallel to the construction of C’s. Twenty days will be required for this activity (each). Assume that the foundations for both abutments are already available and part of this project. d) The caps (EB on the abutment and B on the pier) will be constructed soon after their support structure is completed. Construction of caps will require 6 days each. e) The deck D will be constructed at last to complete the bridge. It will take 20 days to build the deck (D) resting on the set of caps (i.e. EB and B).
• You are required to just include the following resources in this project cost:
Concreter – Labour: Max crew = 8; unit cost = $80/h
Steel Fixer – Labour – Max crew = 8; unit cost = $75/h
Carpenter – Labour – Max crew = 8; unit cost = $70/h
Concrete - $375/cu.m
Steel - $3500/tonne
• Resources to be used for this construction project are given in the table in next page. Apply the resource loading to your schedule.
Prepare your report including:
This MME80001: Management Assignment has been solved by our Management Experts at onlineassignmentbank. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.
Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.
© Copyright 2026 My Uni Papers – Student Hustle Made Hassle Free. All rights reserved.