COURSE: PROJECT MANAGEMENT
TOPIC: PROBABILISTIC ACTIVITY TIMES
zInfinity (aka Zinfinity) is a new-age space exploration company with a mission to commercially exploit the near-Earth objects in the outer space. It is building reusable rockets and space equipment that can be used to mine asteroids and comets in the solar system and bring back the precious metals and minerals to the Earth to make profit. Thanks to Swikileaks, we got hold of some confidential information about zInfinity’s next secret project. While the details of individual activities are not available, we know that the project has 12 key activities. Each activity involves uncertainty, but the engineers at zInfinity have calculated most optimistic, most pessimistic and most likely time for each activity. We also know the relationships among these activities. Even with this limited information, we want to find out about the completion time and various probabilities associated with this project. See the work breakdown structure (in Weeks) and network diagram given below.

WBS IN WEEKS
Activity ID Predecessor Optimistic
Time (a) Most Probable
Time (m) Pessimistic
Time (b)
A None 1 2 3
B A 1 3 5
C A 3 4 5
D A 1 4 7
E B,D3 4 11
F C 1 2 3
G E,F4 6 8
H C 2 3 4
I G 2 4 6
J H 1 2 3
K H 3 4 5
L I,J,K 2 3 4
914400367030

Short Case Report Requirements:
Based on the information given above, prepare a Short Case Report that address the followings:
1. What are the expected time and variance for each of the 12 activities?
2. Which activities are critical and what is the critical path? What is the total project completion time?
3. What is the project variance and project standard deviation?
4. What is the probability that zInfinity will be able to complete the project in 30 weeks?
5. What is the probability that zInfinity will be able to complete the project in 20 weeks?
6. What is the probability that the project will take between 20 and 30 weeks?
7. What is the probability that the project will take longer than 25 weeks?
8. What is the completion time by which there is 99% certainty that the project is completed? 9. What is the completion time by which there is 90% certainty that the project is completed? 10. What is the completion time by which there is 75% certainty that the project is completed?

 

This Management Assignment has been solved by our Management experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.
Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.