Assignment Task :

Task 1

1) List the four (4) stages of Project Life Cycle, and discuss the importance of the final stage. 

2) Through an example briefly explain the meaning of a Work Breakdown Structure (WBS). Why is it important to have such a structure? (6 marks.) 

3) Using the tables below, plot out a full Network Diagram for all projects and identify the critical path. How many days does it take to complete every project? 

4) What is the importance of generating a project closeout report?  

5) What is the purpose of Risk responses in Project Management? Identify and briefly discuss The Four (4) types of responses to risk. 

6) Outline and explain the purpose of Quality audits. Identify the reasons why such methods (Project evaluation, Monitoring, and Control) you would introduce to ensure a project is completed to the correct Quality standard.

 

Task 2: 

“Pump Ltd” is an SME company specializing in the design and supply of pumps. The organizations they are commissioned by includes: Local Authorities, SME enterprises, and - on rare occasions - large global companies. The company has been particularly successful since it started trading in 2005. They trade from a single main warehouse next to the factory that also includes office accommodation (30,000 square meters). At present, the company employs 1 General Manager, 2 Assistant Managers, 3 Administration staff, 4 Design and Sales Staff, 3 supervisors, and 20 General Operations staff. 

As part of a strategy of expansion, “Pump Ltd” has employed you as a Project Manager to manage a one-off special project. This project is concerned with the opening of a building which they recently acquired (50,000 square meters). This new building will allow the company to target and respond to Asia and Middle-East markets for large demands for pumps and must be opened within a 9-month schedule using an investment budget of £750,000. Initially, the new staffing structure at the new building will mirror the existing structure at the existing site. 

As Project Manager responsible for opening the new building for trade, you are required to prepare a report (2,300 words). From a Project management perspective outline the activities required to successfully manage this new initiative, ensuring that it is on time, and within budget. 

The analysis should include the skills and competencies required by the Project Manager, along with the project management process. Use examples of the concerns, Project Life Cycle stages, processes, and leadership, administration, and control problems associated with managing the lifecycle of this major project. 

 

This SIM335 - Strategic Management Assignment has been solved by our Management Experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.

Get It Done! Today

Country
Applicable Time Zone is AEST [Sydney, NSW] (GMT+11)
+

Every Assignment. Every Solution. Instantly. Deadline Ahead? Grab Your Sample Now.