The Current Shelves for Storing Aircraft Parts During Maintenance - Engineering Assignment Help

Download Solution Order New Solution
Assignment Task:

Task:

Engineering design A.1
a) The problem: The current shelves for storing aircraft parts during maintenance are fixed structures in the hangar and the height of three different sections is not been designed to store heavy parts such as gearboxes. The middle shelve is used most of the time. The top shelve is too high to be used and the bottom shelve is too low and as a result there is always a chance of back injury while using the bottom shelve. Also when working away from the hangar, there is no way of transporting these shelves.
There are alternative benches provided when working away from the hangar but most of the time they are not fit for purpose and very hard to move around as they are very heavy items.
The task: To design a product which can be used more efficiently and can be transported with ease with the help of forklifts and can be loaded and unloaded on to a truck for transportation. Also the product should be cost effective to produce.
b) Design comparison: BSI EN 1090 is a harmonized standard that covers structural/construction steel and aluminium products that are installed in a permanent manner. Since our product will be made from structural steel, it must comply with EN 1090-1. All the material for the design will be within regulations of BSI EN 1090-1(Euro code 3). Any material bought will be checked for CE markings by the BSI. These regulations are covered by Scope of EN 1090 document provided by BSI. I have provided a link for the document in reference section of this assignment.
BSI has another provision for new products such as ours which can be certified after their rigorous checks for quality and safety. An application form will be sent once the product is tested for use; it can be checked by one of the BSI representatives and certified according to the requested class.
c) The initial load bearing and design specifications have been taken from previous design used for shelves. In the current design, the safe load bearing calculations have been done according to BSI 1090-1. This still doesn’t certify the design, so the application will be sent to BSI product certification department once the project is complete and tested.
Design specifications: The final product will be a section of 2.5 metre long storage racks with forklift lifting points on each unit. The height of the top shelf will be 680mm and the height of the bottom shelf will be 340mm from the floor which will make it easy to lift heavy parts from the bottom shelf easier. These measurements are in line with BSI safe load lifting height. Also the gap between shelves will provide enough room for bigger parts for storage.
These 2.5 metre long racks can be placed next to each other as a two or 3 according to the type of aircraft and the maintenance to be carried out. There will be forklift lifting points to move the racks and also make them easy to load on a truck for transportation.
19050400685Diagram:
80962519685
Manufacturing and safety requirements: The product will be manufactured from stainless steel and cast iron due to the load carrying during their service life. It can be assembled on site and once assembled, will be easy to use than the previous storage facilities. There is a designated fabrication bay on site with certified EN ISO 14731 fabricators, capable of fabricating all the required parts for the new products. They will do the weight limit tests before it is installed for safety.
Maintenance: The product will be designed to last for a very long period of time with paint protection and minimal inspections required. The painted surface will prevent any contamination from aircraft fluids. These inspections will be very basic and can be done by the user. So no professional maintenance or inspections are required.
Safe usage: The product will be designed to bear loads for 1000 kg per shelve which are more than enough than the previous design with 600kg weight limit. Since the finished product will be heavy and not suitable for manual movement, it can only be moved by forklifts.
Environmental hazards and recycling: Old racks can be fully recycled as they have been manufactured from the same materials. There is a possibility to reuse some of the parts from the old racks and modify them for the new ones. Water based paints will be used and use of packaging will be minimised to reduce environmental impact.
Life cycle: The finished product intends to have a 25 years’ service life.
Patents: N/A
Intended market: The product will be designed for in house company use only.
d) Project planning techniques:
i) Critical path analysis: For huge, complex projects that have an enormous number of exercises that could be acted in equal and where conditions exist between those activities, a 'Critical Path Analysis' is a compelling strategy. It assists with recognizing whether tasks can be run in parallel, the necessary sequence of the activities and their general need inside the task.
Advantages:
1. Activities that can run parallel to each other are determined easily.
2.  It helps the project manager identify the most important elements of the project.
3. It provides a practical and disciplined foundation by which to determine how goals will be achieved.
Disadvantages:
1. Personnel scheduling is not handled by this method. 
2. It is difficult to estimate the completion time of an action. 
3. The critical path could become complicated when time limits are not met.
ii) Gantt Chart: Gantt chart is one of the most useful tools when planning projects. They are used to plan and monitor tasks, report costs and expenses at each stage of the project, report progress and create reports. In a simple flow chart, they represent activities and costs over time in an easy-to-understand form. A Gantt chart can also be created as a set of software tools or spreadsheets.
Advantages:
1. Gantt charts allow you to create a project plan and visualize all the work in one bar chart over time. 
2. Gantt charts allow you to document and understand work dependencies.
3. The Gantt chart requires the task assigned to the owner. As a result, you can see who is working on which task.
Disadvantages:
1.  Software such as Microsoft Project, Smart sheets takes time and effort to set up, especially if you try to incorporate task links from the traditional project management software.
2. Gantt chart can become confusing and complicated for large projects.
3. Too much project detail can make them hard to understand.
I have used Gantt chart for my project due to its various advantages for small project. First of all, the data used for the project is simple and in small quantity, so it is easy to understand and configure in a spreadsheet. As shown in part (e) of this assignment, the data has been entered step by step and critical path clearly shows the undertaking of different stages to complete the project.
e) Gantt Chart: Figure 166675706755
Monthly plan:
-381003048635-38100200660
In the screenshots from the spreadsheets above(Fig.1), the Gantt chart critical analysis clearly shows how each step has been numbered with time constraints. This is where it shows the time frame that each step will be completed and keeps the project on track. Critical Path formally identifies tasks which must be completed on time for the whole project to be completed on time.
In figure 1 above, the task goes through:
Plan Analyse Design Build Test Deliver
Align on project Research supply and demand chain Design and agree on data models to build and simulate Run model simulations Review findings internally and update data as necessary. Review and approve the strategy.
Agree on deliverables Agree to design principles for achieving the target Begin building an initial draft of report. Adjust models and re-run simulations. Deliver the final report.
Validate project team resources and timeline Acknowledge hard constraints Update report findings Level set on soft constraints All the above phases have time limits in which they have to be completed. This is where critical analysis help in a project to manage and understand time limits for each task.
 

The above  Engineering Assignment has been solved by our  Engineering Assignment  Experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our experts are well trained to follow all marking rubrics & referencing style.

Be it a used or new solution, the quality of the work submitted by our assignment experts remains unhampered. You may continue to expect the same or even better quality with the used and new assignment solution files respectively. There’s one thing to be noticed that you could choose one between the two and acquire an HD either way. You could choose a new assignment solution file to get yourself an exclusive, plagiarism (with free Turnitin file), expert quality assignment or order an old solution file that was considered worthy of the highest distinction.