Karabo has been appointed as Project Manager for a project sponsored by Matlosana Local Municipality to supply water to households in Zenda Location in Kanana. Together with his project team, he appoints two performing organisations that will execute the tasks in the project. Karabo holds several meetings with the Engineers of the performing organisations which result in the development of the Work Breakdown Structure shown in Table 1.
Table 1: Work Breakdown Structure for Zenda Water Project
Expanded WBS
Task Description Duration (days) Predecessors Resource
1 Civil works I Herminah
1.1 Drill borehole 1 - Jack
1.2 Construct pump house 2 - Omphile
1.3 Construct reservoir 4 - Oratile
1.4 Excavate trench from pump house to reservoir 2 - Nkate
1.5 Excavate trenches for distribution (reticulation) of water from reservoir to households 3 - Tebogo
2 Mechanical works Katlego
2.1 Install borehole pipe 1 1.1 Tshenolo
2.2 Install pump 1 1.2 Mogale
2.3 Connect pump to borehole pipe 1 1.1, 1.2 James
2.4 Install pipeline to connect pump to reservoir 2 1.4 Greg
2.5 Install pipeline to distribute water from reservoir to households 3 1.5 Van Wyk
2.6 Pump water to reservoir 1 2.3, 2.4 Matsego
2.7 Supply water to households 1 2.5, 2.6 Noe
2.8 Check for and fix leakages in pipelines 2 2.7 Bob
2.9 Cover trenches 2 2.8 Joe
2.10 Pay contractors 1 2.9 Karabo
2.11 Handover project 1 2.10 Karabo
Required:
3.1 Develop a Gantt chart for this project by completing the template attached as Appendix 1.
This Management Assignment has been solved by our Management experts at My Uni Paper. Our Assignment Writing Experts are efficient to provide a fresh solution to this question. We are serving more than 10000+ Students in Australia, UK & US by helping them to score HD in their academics. Our Experts are well trained to follow all marking rubrics & referencing style.